CASE STUDY – Charlotte NC Kitchen Renovation 

I picked Charlotte as a representative city where construction costs are in the middle of the range nationally.  Other places the costs could vary substantially.   

This was the entire prompt pasted into the Budget Game.

“We have a 350sf kitchen in our 1948 home in Charlotte, NC, with a basement below. We want to fully renovate it: new cabinets, counters, appliances, and we’d like to move the sink to a different wall and add an island with a prep sink.”

After a dozen questions, investigation of alternates for cabinets and appliances. This was the output.   I took less than 30 minutes.  Once you have this kind of budget, you can go back to the same chat, look at all the detail carefully, add photos, ask questions, research finishes and products and make changes as long as you find it useful.  You can even set a lower spending limit, and the Budget Game will suggest a scope.  

The Budget Game — Budget & Scope Summary

350 SF Kitchen Remodel — 1948 Home, Charlotte, NC

PROJECT 1: KITCHEN REMODEL

350 SF Kitchen — 1948 Home, Charlotte, NC — Full Remodel, Sink Relocation, New Island, New Oak Floor

Section 1 — Summary Budget

Note that this budget is based on very preliminary description of the project and provides only a ROUGH-ORDER-OF-MAGNITUDE number that can serve as the basis for further investigation.

SectionSub-item%Cost
Demolition 1.8%$1,790
Asbestos Testing & AbatementVAT — PLACEHOLDER, pending actual test result5.2%$5,000
Plumbing 6.4%$6,200
Electricalincl. confirmed 200A panel upgrade12.2%$11,850
Carpentry/Blocking 0.6%$600
Drywall PatchPLACEHOLDER, pending photos0.6%$600
Flooringnew oak, to match living/dining4.7%$4,550
CabinetsWood-Mode, high-grade base49.5%$48,000
Countertopsquartz4.8%$4,675
AppliancesViking 30″ gas range + GE fridge/DW/hood12.3%$11,900
Paint 1.4%$1,400
Trim 0.4%$350
Trade Cost Subtotal  $96,915
General Conditions12% of Trade Subtotal12%$11,630
Contractor Fee10% of (Trade + GC)10%$10,855
Contractor Total  $119,400
Soft Costs Subtotalpermits, incl. asbestos notification $1,600
Total Before Contingency  $121,000
Owner’s Contingency30% of Total Before Contingency30%$36,300
GRAND TOTAL  $157,300

Alternates:

  • Deductive Alt — Cabinets: KraftMaid mid-grade instead of Wood-Mode high-grade: –$46,100

Your eye may be drawn to that 30% contingency — it’s a big number. These budgets look like ones based on weeks of detailed work, but this is still a rough estimate. The contingency covers uncertainty in the pricing, cost escalation between now and construction, and — honestly — you changing your mind along the way. I recommend leaving it in for now. For a fuller discussion of contingency, go to the Project Therapy piece, Contingency, Your Best Friend

Section 2 — Detailed Budget

Note that this budget is based on very preliminary description of the project and provides only a ROUGH-ORDER-OF-MAGNITUDE number that can serve as the basis for further investigation.

DescriptionQty/Units%Unit CostTotal Cost
DEMOLITION    
Remove base/wall cabinets52 LF $10/LF$520
Remove countertops30 LF $10/LF$300
Remove/disconnect appliances4 EA $75/EA$300
Cap existing sink & disconnect plumbing1 EA $150/EA$150
Debris haul/dumpster1 EA $520/EA$520
ASBESTOS TESTING & ABATEMENT    
Lab testing of VAT — PLACEHOLDER pending actual test1 EA $400/EA$400
Licensed VAT abatement removal350 SF $10/SF$3,500
Containment/negative air setup1 EA $600/EA$600
Subfloor prep after abatement1 EA $500/EA$500
PLUMBING    
Relocate main sink rough-in (new wall)1 EA $1,200/EA$1,200
New island sink rough-in + loop vent1 EA $2,200/EA$2,200
Dishwasher supply/drain1 EA $350/EA$350
Refrigerator ice maker line1 EA $250/EA$250
Main sink fixture1 EA $650/EA$650
Island bar/prep sink fixture1 EA $450/EA$450
Faucets2 EA $300/EA$600
Garbage disposals2 EA $250/EA$500
ELECTRICAL    
Panel upgrade, 100A to 200A (confirmed)1 EA $5,200/EA$5,200
Range/oven circuit1 EA $450/EA$450
Dishwasher circuit1 EA $350/EA$350
Disposal circuits2 EA $250/EA$500
Microwave/hood circuit1 EA $350/EA$350
Refrigerator circuit1 EA $300/EA$300
Island receptacle circuits2 EA $200/EA$400
GFCI countertop receptacles6 EA $150/EA$900
Under-cabinet lighting1 EA $650/EA$650
Recessed lighting8 EA $200/EA$1,600
Island pendant lighting3 EA $250/EA$750
Switches/dimmers1 EA $400/EA$400
CARPENTRY    
Blocking for island/cabinets1 EA $600/EA$600
DRYWALL    
Patch at relocated plumbing/electrical — PLACEHOLDER pending photos4 EA $150/EA$600
FLOORING    
New oak hardwood, site-finished, to match existing living/dining350 SF $13/SF$4,550
CABINETS    
Custom cabinetry, high-grade (Wood-Mode) — base/wall/island64 LF $750/LF$48,000
COUNTERTOPS    
Quartz, perimeter + island55 SF $85/SF$4,675
APPLIANCES    
Range/oven, Viking 30″ gas1 EA $8,500/EA$8,500
Refrigerator, GE1 EA $2,200/EA$2,200
Dishwasher, GE1 EA $700/EA$700
Range hood/microwave, GE1 EA $500/EA$500
PAINT    
Walls, ceiling, trim1 EA $1,400/EA$1,400
TRIM    
Casing repair at patched areas1 EA $350/EA$350
TRADE COST SUBTOTAL   $96,915
General Conditions 12% $11,630
Contractor Fee 10% $10,855
CONTRACTOR TOTAL   $119,400
SOFT COSTS    
Electrical permit1 EA $350/EA$350
Plumbing permit1 EA $300/EA$300
Building/renovation permit1 EA $600/EA$600
Asbestos abatement notification1 EA $350/EA$350
SOFT COSTS SUBTOTAL   $1,600
TOTAL BEFORE CONTINGENCY   $121,000
Owner’s Contingency 30% $36,300
GRAND TOTAL   $157,300

Alternates (fully loaded): Deductive Alt — Cabinets: KraftMaid mid-grade instead of Wood-Mode high-grade: –$46,100

MARKET SPOT-CHECK: A general survey of the Charlotte market places a full kitchen remodel with layout changes and premium finishes in the $150,000–$250,000 range.

SCOPE DOCUMENT

What is being built

  • Full renovation of the 350 SF kitchen in a 1948 Charlotte, NC home
  • New high-grade custom cabinets (Wood-Mode), quartz countertops
  • Main kitchen sink relocated to a new wall
  • New island with a bar/prep sink
  • New appliances: Viking 30″ gas range, GE refrigerator, GE dishwasher, GE range hood/microwave
  • Electrical panel upgraded from 100A to 200A, with new circuits for all appliances, island, and lighting
  • New oak hardwood flooring installed in the kitchen, matched to the existing living/dining room hardwood
  • Existing vinyl asbestos tile (VAT) removed via licensed abatement
  • Alternate project (in place of the kitchen, if preferred): sand and refinish existing hardwood floors in the living room (400 SF) and dining room (300 SF), matching current stain color, done in one pass while the home is unoccupied

What is not included

  • Any layout change beyond the sink relocation and island addition (no wall removal)
  • Backsplash tile
  • Design or space-planning drawings (this tool works in text only)
  • Housing costs for the household during construction
  • Combining the kitchen project and the floor-refinish alternate into one job — priced as two separate options, per how the project was described

Key assumptions made

  • Cabinet run: 64 linear feet total (base, wall, and island), based on the described layout (two full walls plus part of a third, plus an island)
  • VAT priced assuming it tests positive for asbestos and requires licensed abatement — a negative test would reduce this cost substantially
  • Existing hardwood species assumed to be oak (as stated) for the new kitchen floor match
  • Standard non-union residential labor rates
  • No structural work involved (no wall removal, no foundation/framing changes)

Unanswered questions still outstanding

  • Photos of the existing kitchen have not been provided
  • The VAT has not yet actually been lab-tested for asbestos

PLANNING & BUILDING CODE SUMMARY

RESOLVED

  • Permits: this project involves plumbing, electrical, and gas work, so building, electrical, and plumbing permits are required — confirmed and priced in as soft costs.

OUTSTANDING — CONFIRM WITH YOUR LOCAL PLANNING OR BUILDING DEPARTMENT

  • Asbestos in the existing VAT: unconfirmed by actual lab test. North Carolina requires a certified inspection and a notification to the state’s Asbestos Hazard Management Program before renovation begins, even if the result comes back negative — this affects both cost and how demolition has to be sequenced. Confirm with: https://epi.publichealth.nc.gov/asbestos/demolition.html
  • Permits for this project are issued by Mecklenburg County (not the City of Charlotte directly) — confirm exact permit requirements and fees before construction: https://www.meckpermit.com